Moray East Document Library

Our document library page contains environmental statements, reports, applications, and general information about the project. This material is for the general public.


Thumbnail
PDF file icon
Appendix 5 6 A Socio economics
PDF file icon
Appendix 5 7 A Consultee Responses
PDF file icon
Appendix 5 7 B Traffic Flow Data
PDF file icon
Appendix 5 7 C Future Traffic Baseline
PDF file icon
Appendix 7 3 A Marine Mammals Impact Assessment
PDF file icon
Appendix 7 3 B Underwater Noise Assessment Framework
PDF file icon
Appendix 7 3 C SAFESIMM Impact Assessment
PDF file icon
Appendix 7 3 D Behavioural Responses to Noise
PDF file icon
Appendix 7 3 E Noise Exposure Criteria for Pinnipeds
PDF file icon
Appendix 7 3 F Underwater Noise Propagation Modelling

Moray East Key Facts

  • Consent for construction of up to 1,116MW granted in 2016
  • CfD for 950MW awarded in 2017
  • Connection to National Grid at a new substation to be constructed at New Deer in Aberdeenshire via underground cable (planning permission granted by Aberdeenshire Council in 2014)
  • Total underground export cable corridor route 86km (52km offshore and 34km onshore)
  • Total wind farm Area – 295km2
  • Maximum turbine blade-tip height – 204m (669 feet)
  • Minimum distance from shore – 22km (13.5 miles).